Zirku Onshore Facilities - New Contractors Camp

  • Contract Value: AED 76.92 Million
  • Contract Duration: 27 Months
  • Client/ Owner: Zakum Development Company (ZADCO)
  • Design Consultant: GIBB-Jacob Engineering
  • Main Contractor: ACTCO
  • Completion Date: Expected in Dec 2015
 

This project is on Zirku Island, 100km offshore of the Abu Dhabi coast. The project has three accommodation buildings for staff, with a hub building and substation buildings providing necessary amenities.

Scope of work includes supply, installation, testing and commissioning of the following:

Lighting:

- Street lighting, landscape and building lighting and emergency lighting

Electrical Power systems:

- 22kV MV Switchgear
- MV Substation with RMU
- 2300m route length of MV Cabling
- LV Cabling
- LV Switchgear
- Transformers – 4 Nos x 2000kVA
- DC UPS for ELV Systems

Low Current and Security systems:

- Public Address System
- TEL & Data System – with Structured Cabling and OFC Network System
- CATV distribution
- Addressable Fire Alarm System
- ASD / VESDA System for void protection

Mechanical & Plumbing Works:

- Seawater Firefighting System with external GRE piping and CuNi Sprinkler System
- 14 Nos. 135TR chillers, AHUs, CHW Pumping System
- 900 Nos. FCUs
- 53TR VRF System with ductable and decorative indoor units
- DX System for substation
- UG Sewerage Pumping Station
- IG -541 Fire Protection System for HV/LV room