Client/owner :

Dubai Properties

Completion date :

2016

  • SHARE PROJECT

Majan District Phase 2, Infrastructure Work

13
Contract
duration (months)

ABOUT THE BUILD

The project consisted of one irrigation and fire pump station with 3 irrigation pumps, 3 fire pumps and 1 sump pump, and one storm water pumping station with 6 storm water pumps.

The scope of work included the supply, installation, testing and commissioning of the above pumps, including all necessary panels, piping, valves and related accessories.

Trans Gulf Electromechanical LLC executed the below mentioned scope:

HVAC and Plumbing

  • GI pipes and fittings
  • GRP pipes and fittings
  • Misc
  • Irrigation pumps
  • Valves and accessories
  • SS penstock and GRP kiosk
  • Sump pumps - storm water
  • Fire pumps
  • Instrumentation
  • Split AC units and extractor fans
  • FM200 and fire extinguishers
  • Bar screen, auto screen filter and pr. vessel
  • EOT crane

Electrical & ELV Systems

  • Motor control centre
  • Estimated
  • Distribution boards
  • Feeder pillar
  • Meter cabinet
  • RTU panels/SCADA
  • HV cabling (3C 300mm2 XLPE/STA/PVC)
  • LV cabling
  • Containment (trays and ladders)
  • Earthing system
  • Lightning protection system
  • Wiring accessories
  • Light fittings
  • Emergency/exit light fittings
  • Fire alarm system