Dubai Healthcare City District Cooling Plant - Empower

14
Contract
duration (months)

ABOUT THE BUILD

Dubai Healthcare City District Cooling Plant – Empower. Trans Gulf was responsible for the design and development of engineering drawings, plant and material selection, procurement, installation, commissioning and performance validation of the mechanical and electrical chilled water process plant for the district cooling system at Healthcare City.

Trans Gulf’s scope of work included the following:

  • Design and construct 2 x 60,000 TR district cooling plants with 8 x 2 lead/lag packaged chiller modules of 5,000 TR each
  • 8 cooling towers of 5,000 TR
  • Associated MV/LV switchgear
  • SCADA – plant control and monitoring system
  • 7400 cubic metre ground water storage tanks
  • Operation and maintenance for two years

The project provides chilled water to Healthcare City including commercial and showroom buildings, residential buildings and town houses.